Fronius Spain
One plan for 10 inverters of 6 different models
- Type
- Technical validation pilot
- Inverters
- 10 inverters, 6 models
- Batteries
- BYD and Fronius Reserva
- Location
- Getafe (Madrid)
- Dates
- 28 Jun – 13 Sep 2026
- Duration
- 11 weeks

Results
< 2 s
zero export corrected
Measured at the site's gateway.
−14 %
battery cycles
Against the inverter's default self-consumption mode.
10
inverters on one plan
Of 6 models, two of them hybrids with a battery.
What the installer and Fronius saw


10 inverters, 6 models and 2 batteries in one dashboard.
Hover over or tap the gold dots.
Stops export without giving up the battery
It charges the battery first; only then curtails PV, shared across inverters.
What was validated
- 10 inverters coordinated by one plan
- Two battery brands at once
- Zero export at the gateway